<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=459021408546817&amp;ev=PageView&amp;noscript=1">
Contact

09/25 - 10/06

  • Complete Steel Framing & Decking through Level 15
  • Complete Concrete Placement through Levels 10-11
  • Continue Intumescent Paint & Spray Fireproofing of lower levels (01-04)
  • Continue prep for landscape @ Congress Street & WTC Ave
  • Continue prep for curtainwall through Level 12
  • Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.

Night & Weekend Work:

  • Saturday Day Shift Work to be requested on case-by-case basis. 
  • Fire Protection piping in Congress St @ Triangle Parcel: complete
  • Pedestrian Bridge Steel welding: Thursday 9/21 (11pm-5am). Ramp F closed to..
Read More

Construction Archive

09/25 - 10/06

Complete Steel Framing & Decking through Level 15 Complete Concrete Placement through Levels 10-11 Continue Intumescent Paint & Spray Fireproofing of lower...

09/18 - 09/29

Complete Steel Framing & Decking through Level 14 Complete Concrete Placement through Levels 10-11 Pour concrete @ Slab on Grade & Mezzanine Continue...

09/11 - 09/22

Complete Steel Framing & Decking through Level 13 Complete Concrete Placement through Level 09 Pour concrete @ Basement Continue spray Fireproofing of lower...

09/05 - 09/15

Complete Steel Framing & Decking through Level 13 Complete Concrete Placement through Level 08 Pour concrete @ Basement Continue spray Fireproofing of lower...

08/28 - 09/08

Complete Steel Framing & Decking through Level 12 Complete Concrete Placement through Level 08 Pour concrete @ Basement Continue spray Fireproofing of lower...

08/14 - 08/25

Complete Steel Framing & Decking through Level 10 Complete Concrete Placement through Level 07 Start concrete @ Auditorium seating Continue excavation for...

08/07 - 08/18

Complete Steel Framing & Decking through Level 09 Complete Concrete Placement through Level 07 Excavation for Basement along Congress Street Start Spray...

07/31 - 08/11

Complete Steel Framing & Decking through Level 08 Complete Concrete Placement through Levels 04 Excavation for Basement along Congress Street Start Spray...

07/24 - 08/04

Complete Steel Framing & Decking through Level 07 Complete Concrete Placement through Levels 02 Form & pour Level 03 deck Excavation for Basement along...

07/17 - 07/28

Complete Steel Framing & Decking through Level 06 Complete Concrete Placement through Levels 02 Complete Steel Framing through Level 07 Form & pour Level 03...

07/10 - 07/21

Complete Steel Framing & Decking through Level 05 Complete Concrete Placement through Level 02 Continue Steel Framing through Level 06 Form & pour Level 03...

06/26 - 07/07

Continue Level 04 framing Complete Steel Framing & Decking through Level 04 Complete Concrete Placement through Level 02 Continue Steel Framing through Level...

06/19 - 06/30

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...

06/12 - 06/23

Continue Level 04 framing Continue steel detailing at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend work for...

06/05 - 06/16

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...

05/29 - 06/09

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...

05/22 - 06/02

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) See night/weekend work for Pedestrian Bridge information ...

05/15-05/26

Continue Levels 03-04 framing Continue install of overhead protection work at highway ramp Continue steel assembly / detailing on Triangle Parcel ...

05/08-05/19

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Complete detailing of...

05/01-05/12

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...

04/24-05/05

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...

04/03-04/13

Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Levels 2 - 3. Continued below-grade work throughout...

04/18-04/28

Patriots’ Day / Marathon Monday (04/17): No work on site. Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at...

04/10-04/21

Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Level 03. Pour tower core slab Levels 04-05 Continue...

03/27-04/07

Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...

03/20-03/31

Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...

03/13-03/24

Demobilize core climber. Continue below-grade work along west and north of A-2 site. Prepare for assembly of East arch (alongside WTC Ave). Continue...

03/06-03/17

Tower Core Wall Reinforcement & Installation (Level 17-Roof) Steel arch assembly for South Arch (opposite Congress Street) Steel frame erection of Level 01...

02/27-03/10

Continue installation of pile caps, waterproofing, and grade beams Concrete Tower Core (Levels 13-16) Steel arches have arrived! Assembly starting along...

UPCOMING WORK

01/30-02/10 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...

UPCOMING WORK

01/23-02/03 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...

UPCOMING WORK

01/16-01/27 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...

UPCOMING WORK

01/09-01/20 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
Load More