6/17/24 - 6/28/24

  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Triangle Geofoam Placement/Switchback Ramp FRP/Waterproofing
  • Curtain Wall Installation L16/17-Upcoming
  • Loading Dock- Structure and MEPFP Install
  • Lobby Rough MEP & Framing- Core Wall and Dome Ceiling
  • Lobby Wood Ceiling Install
  • Elevators- Service Cars, Low Rise, and High Rise Ongoing
  • Recharge System #2
  • WTC Ave Demo/Hardscape

Night & Weekend Work:

  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Week of 6/17- M-Th Ramp D Closures- Triangle Façade..
Read More

Construction Archive

05/13 - 5/31

Penthouse- Framing, Equipment- Connections/Rough MEP Install Mechanical Riser Install/Shaft Framing Rough Mechanical Installation Curtain Wall Bunk...

05/07 - 5/24

Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching) Mechanical Riser Install/Shaft Framing Rough Mechanical...

4/22 - 5/10

Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching) Mechanical Riser Install/Shaft Framing Rough Mechanical...

4/8 - 4/26

Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical...

3/26 - 4/12

Penthouse Equipment deliveries/hoisting Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical Installation Curtain...

3/18 - 4/5

Penthouse Equipment deliveries/hoisting Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical Installation ...

3/12 - 3/29

Penthouse Equipment deliveries/hoisting Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical Installation ...

2/26 - 3/15

Penthouse Equipment deliveries/hoisting Spray Fireproofing (L18, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical Installation Curtain...

2/12 - 2/23

Concrete Slab on Deck Placements (roof level) Spray Fireproofing (Dome Ceiling) Mechanical / Elevator shaft framing Lobby MEPs Curtain Wall Bunk deliveries...

1/29 - 2/9

Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...

1/15 - 1/26

Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...

1/2 - 1/12

Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...

1/2 - 1/12

Steel Detailing(roof level) Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck...

12/18 - 12/29

Steel/Deck Erection (roof decking & framing) Slab on Deck reinforcements and MEP penetrations (L17) Concrete Slab on Deck Placements (L17 South and L17...

12/11 - 12/22

Steel/Deck Erection (roof decking & framing) Slab on Deck reinforcements and MEP penetrations (L17) Concrete Slab on Deck Placements (L17 South and L17...

12/05 - 12/15

Steel/Deck Erection(18 Metal Decking, 18&19 framing) Slab on Deck reinforcements and MEP penetrations (L16 and L17) Concrete Slab on Deck Placements (L15...

11/28 - 12/8

Steel/Deck Erection(18 Metal Decking, 18&19 framing) Slab on Deck reinforcements and MEP penetrations (L16 and L17) Concrete Slab on Deck Placements (L15...

11/06 - 11/17

Complete Concrete Placement through Level 15 Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 12) Continue prep for...

10/30 - 11/10

Steel framing complete through roof Install Monument Stair between Levels 01-02 Complete Concrete Placement through Level 14 Continue Intumescent Paint &...

10/23-11/03

Complete Steel Framing & Decking through Roof Topping Out Ceremony to take place Thursday 10/26: 11am-1pm @ WTC Ave Plaza Install Monument Stair between...

10/02 - 10/13

Complete Steel Framing & Decking through Level 16 Complete Concrete Placement through Levels 11-12 Continue Intumescent Paint & Spray Fireproofing of lower...

09/25 - 10/06

Complete Steel Framing & Decking through Level 15 Complete Concrete Placement through Levels 10-11 Continue Intumescent Paint & Spray Fireproofing of lower...

09/18 - 09/29

Complete Steel Framing & Decking through Level 14 Complete Concrete Placement through Levels 10-11 Pour concrete @ Slab on Grade & Mezzanine Continue...

09/11 - 09/22

Complete Steel Framing & Decking through Level 13 Complete Concrete Placement through Level 09 Pour concrete @ Basement Continue spray Fireproofing of lower...

09/05 - 09/15

Complete Steel Framing & Decking through Level 13 Complete Concrete Placement through Level 08 Pour concrete @ Basement Continue spray Fireproofing of lower...

08/28 - 09/08

Complete Steel Framing & Decking through Level 12 Complete Concrete Placement through Level 08 Pour concrete @ Basement Continue spray Fireproofing of lower...

08/14 - 08/25

Complete Steel Framing & Decking through Level 10 Complete Concrete Placement through Level 07 Start concrete @ Auditorium seating Continue excavation for...

08/07 - 08/18

Complete Steel Framing & Decking through Level 09 Complete Concrete Placement through Level 07 Excavation for Basement along Congress Street Start Spray...

07/31 - 08/11

Complete Steel Framing & Decking through Level 08 Complete Concrete Placement through Levels 04 Excavation for Basement along Congress Street Start Spray...

07/24 - 08/04

Complete Steel Framing & Decking through Level 07 Complete Concrete Placement through Levels 02 Form & pour Level 03 deck Excavation for Basement along...

07/17 - 07/28

Complete Steel Framing & Decking through Level 06 Complete Concrete Placement through Levels 02 Complete Steel Framing through Level 07 Form & pour Level 03...

07/10 - 07/21

Complete Steel Framing & Decking through Level 05 Complete Concrete Placement through Level 02 Continue Steel Framing through Level 06 Form & pour Level 03...

06/26 - 07/07

Continue Level 04 framing Complete Steel Framing & Decking through Level 04 Complete Concrete Placement through Level 02 Continue Steel Framing through Level...

06/19 - 06/30

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...

06/12 - 06/23

Continue Level 04 framing Continue steel detailing at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend work for...

06/05 - 06/16

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...

05/29 - 06/09

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...

05/22 - 06/02

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) See night/weekend work for Pedestrian Bridge information ...

05/15-05/26

Continue Levels 03-04 framing Continue install of overhead protection work at highway ramp Continue steel assembly / detailing on Triangle Parcel ...

05/08-05/19

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Complete detailing of...

05/01-05/12

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...

04/24-05/05

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...

04/03-04/13

Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Levels 2 - 3. Continued below-grade work throughout...

04/18-04/28

Patriots’ Day / Marathon Monday (04/17): No work on site. Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at...

04/10-04/21

Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Level 03. Pour tower core slab Levels 04-05 Continue...

03/27-04/07

Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...

03/20-03/31

Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...

03/13-03/24

Demobilize core climber. Continue below-grade work along west and north of A-2 site. Prepare for assembly of East arch (alongside WTC Ave). Continue...

03/06-03/17

Tower Core Wall Reinforcement & Installation (Level 17-Roof) Steel arch assembly for South Arch (opposite Congress Street) Steel frame erection of Level 01...

02/27-03/10

Continue installation of pile caps, waterproofing, and grade beams Concrete Tower Core (Levels 13-16) Steel arches have arrived! Assembly starting along...

UPCOMING WORK

01/30-02/10 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...

UPCOMING WORK

01/23-02/03 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...

UPCOMING WORK

01/16-01/27 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...

UPCOMING WORK

01/09-01/20 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...