<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=459021408546817&amp;ev=PageView&amp;noscript=1">
Contact
Apr 26, 2023

04/24-05/05

  • Grade beams complete – continue utilities connections on site.
  • Continue Level 02 south framing (see below re: Ramp F traffic impacts)
  • Start assembly of West arch
  • Continue steel assembly / detailing at Levels 03-04.
  • Continue below-grade & prepare for structural steel at Triangle Parcel.

Night & Weekend Work:

  • RAMP F CLOSURES: 11pm-5am Weeknights Only.(Monday, Tuesday, Wednesday, Thursday)
    • See Traffic Advisory, to be updated weekly.

  • Suffolk/Pembroke to review cut & cap impacts (status of Seaport West, Seaport Hotel, Seaport East?)
  • Delivery of Triangle Steel scheduled for week of May 1st. Night shift to be confirmed.
  • Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated on Saturdays.