<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=459021408546817&amp;ev=PageView&amp;noscript=1">
Contact
Jan 18, 2024

1/15 - 1/26


  • Elevator Support Steel Installation
  • Slab on Deck reinforcements and MEP penetrations (roof level)
  • Concrete Slab on Deck Placements (roof level)
  • Spray Fireproofing  (Level 17)
  • Mechanical / Elevator shaft framing
  • Rough Mechanical Installation
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM.
  • Curtainwall embed install (Level 18)
  • Curtain Wall Installation (Levels 06-07)
  • Spray Insulation Application- Dome Ceiling and Loading Dock
  • Monument Stair concrete pour (Levels 01-02)

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • One Additional Hoist Jump Upcoming- Roof Access- Date TBD