Apr 11, 2024

4/8 - 4/26


  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Spray Fireproofing  (Patching, Triangle)
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM. 
  • Curtain Wall Installation L13/14/15
  • Lobby MEP Installation
  • Lobby Rough Framing- Core Wall and Dome Ceiling
  • Lobby Storefront Glass Install
  • Elevators- Service Cars and Low Rise Ongoing, High Rise Enabling Work

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Curtainwall Installation SW Side