4/22 - 5/10
Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching) Mechanical Riser Install/Shaft Framing Rough Mechanical...
Continue steel assembly / detailing at Level 03.
Continue below-grade & prepare for structural steel at Triangle Parcel.
Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)
Seeking agency approval for night work Tuesday April 18th through Friday May 5th.
Hours restricted to 11pm-5am, Monday night through Friday morning.
Seeking final information & agency approval for (1) one night water cut-off on Congress Street.
Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated on Saturdays.