01/16-01/27 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
01/09-01/20 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
During the first week of December, foundation work was completed, including the installation of LBE's, Drilled-in Mini Piles, and Pressure Injected Footings...
In October, the first phase of the custom art scrim project was installed at the Congress Street level. In addition to showcasing 21 custom art pieces from a...