Sep 28, 2023 09/25 - 10/06 Complete Steel Framing & Decking through Level 15 Complete Concrete Placement through Levels 10-11 Continue Intumescent Paint & Spray Fireproofing of lower... Read More
Sep 21, 2023 09/18 - 09/29 Complete Steel Framing & Decking through Level 14 Complete Concrete Placement through Levels 10-11 Pour concrete @ Slab on Grade & Mezzanine Continue... Read More
Sep 14, 2023 09/11 - 09/22 Complete Steel Framing & Decking through Level 13 Complete Concrete Placement through Level 09 Pour concrete @ Basement Continue spray Fireproofing of lower... Read More