<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=459021408546817&amp;ev=PageView&amp;noscript=1">
Contact

Construction Updates

FEATURED STORY

05/07 - 5/24

  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Spray Fireproofing  (Patching)
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • ...

FILTER BY

May 9, 2024

05/07 - 5/24

Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching) Mechanical Riser Install/Shaft Framing Rough Mechanical...
Apr 25, 2024

4/22 - 5/10

Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching) Mechanical Riser Install/Shaft Framing Rough Mechanical...
Apr 11, 2024

4/8 - 4/26

Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical...
Mar 28, 2024

3/26 - 4/12

Penthouse Equipment deliveries/hoisting Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical Installation Curtain...
Mar 21, 2024

3/18 - 4/5

Penthouse Equipment deliveries/hoisting Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical Installation ...
Mar 14, 2024

3/12 - 3/29

Penthouse Equipment deliveries/hoisting Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical Installation ...
Feb 29, 2024

2/26 - 3/15

Penthouse Equipment deliveries/hoisting Spray Fireproofing (L18, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical Installation Curtain...
Feb 27, 2024

2/12 - 2/23

Concrete Slab on Deck Placements (roof level) Spray Fireproofing (Dome Ceiling) Mechanical / Elevator shaft framing Lobby MEPs Curtain Wall Bunk deliveries...
Feb 23, 2024

1/29 - 2/9

Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...
Jan 18, 2024

1/15 - 1/26

Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...
Jan 11, 2024

1/2 - 1/12

Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...
Jan 4, 2024

1/2 - 1/12

Steel Detailing(roof level) Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck...
Dec 21, 2023

12/18 - 12/29

Steel/Deck Erection (roof decking & framing) Slab on Deck reinforcements and MEP penetrations (L17) Concrete Slab on Deck Placements (L17 South and L17...
Dec 14, 2023

12/11 - 12/22

Steel/Deck Erection (roof decking & framing) Slab on Deck reinforcements and MEP penetrations (L17) Concrete Slab on Deck Placements (L17 South and L17...
Dec 7, 2023

12/05 - 12/15

Steel/Deck Erection(18 Metal Decking, 18&19 framing) Slab on Deck reinforcements and MEP penetrations (L16 and L17) Concrete Slab on Deck Placements (L15...
Nov 30, 2023

11/28 - 12/8

Steel/Deck Erection(18 Metal Decking, 18&19 framing) Slab on Deck reinforcements and MEP penetrations (L16 and L17) Concrete Slab on Deck Placements (L15...
Nov 9, 2023

11/06 - 11/17

Complete Concrete Placement through Level 15 Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 12) Continue prep for...
Nov 2, 2023

10/30 - 11/10

Steel framing complete through roof Install Monument Stair between Levels 01-02 Complete Concrete Placement through Level 14 Continue Intumescent Paint &...
Oct 26, 2023

10/23-11/03

Complete Steel Framing & Decking through Roof Topping Out Ceremony to take place Thursday 10/26: 11am-1pm @ WTC Ave Plaza Install Monument Stair between...
Oct 5, 2023

10/02 - 10/13

Complete Steel Framing & Decking through Level 16 Complete Concrete Placement through Levels 11-12 Continue Intumescent Paint & Spray Fireproofing of lower...
Sep 28, 2023

09/25 - 10/06

Complete Steel Framing & Decking through Level 15 Complete Concrete Placement through Levels 10-11 Continue Intumescent Paint & Spray Fireproofing of lower...
Sep 21, 2023

09/18 - 09/29

Complete Steel Framing & Decking through Level 14 Complete Concrete Placement through Levels 10-11 Pour concrete @ Slab on Grade & Mezzanine Continue...
Sep 14, 2023

09/11 - 09/22

Complete Steel Framing & Decking through Level 13 Complete Concrete Placement through Level 09 Pour concrete @ Basement Continue spray Fireproofing of lower...
Sep 7, 2023

09/05 - 09/15

Complete Steel Framing & Decking through Level 13 Complete Concrete Placement through Level 08 Pour concrete @ Basement Continue spray Fireproofing of lower...
Aug 31, 2023

08/28 - 09/08

Complete Steel Framing & Decking through Level 12 Complete Concrete Placement through Level 08 Pour concrete @ Basement Continue spray Fireproofing of lower...
Aug 17, 2023

08/14 - 08/25

Complete Steel Framing & Decking through Level 10 Complete Concrete Placement through Level 07 Start concrete @ Auditorium seating Continue excavation for...
Aug 11, 2023

08/07 - 08/18

Complete Steel Framing & Decking through Level 09 Complete Concrete Placement through Level 07 Excavation for Basement along Congress Street Start Spray...
Aug 3, 2023

07/31 - 08/11

Complete Steel Framing & Decking through Level 08 Complete Concrete Placement through Levels 04 Excavation for Basement along Congress Street Start Spray...
Jul 27, 2023

07/24 - 08/04

Complete Steel Framing & Decking through Level 07 Complete Concrete Placement through Levels 02 Form & pour Level 03 deck Excavation for Basement along...
Jul 20, 2023

07/17 - 07/28

Complete Steel Framing & Decking through Level 06 Complete Concrete Placement through Levels 02 Complete Steel Framing through Level 07 Form & pour Level 03...
Jul 13, 2023

07/10 - 07/21

Complete Steel Framing & Decking through Level 05 Complete Concrete Placement through Level 02 Continue Steel Framing through Level 06 Form & pour Level 03...
Jun 29, 2023

06/26 - 07/07

Continue Level 04 framing Complete Steel Framing & Decking through Level 04 Complete Concrete Placement through Level 02 Continue Steel Framing through Level...
Jun 22, 2023

06/19 - 06/30

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...
Jun 15, 2023

06/12 - 06/23

Continue Level 04 framing Continue steel detailing at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend work for...
Jun 8, 2023

06/05 - 06/16

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...
Jun 1, 2023

05/29 - 06/09

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) Curtainwall Embeds – Level 02 Pour Level 02 deck See night/weekend...
May 25, 2023

05/22 - 06/02

Continue Levels 03-04 framing Continue steel welding & decking at Triangle Parcel (park) See night/weekend work for Pedestrian Bridge information ...
May 18, 2023

05/15-05/26

Continue Levels 03-04 framing Continue install of overhead protection work at highway ramp Continue steel assembly / detailing on Triangle Parcel ...
May 11, 2023

05/08-05/19

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Complete detailing of...
May 4, 2023

05/01-05/12

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...
Apr 26, 2023

04/24-05/05

Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...
Apr 26, 2023

04/03-04/13

Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Levels 2 - 3. Continued below-grade work throughout...
Apr 20, 2023

04/18-04/28

Patriots’ Day / Marathon Monday (04/17): No work on site. Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at...
Apr 13, 2023

04/10-04/21

Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Level 03. Pour tower core slab Levels 04-05 Continue...
Apr 4, 2023

03/27-04/07

Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...
Mar 23, 2023

03/20-03/31

Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...
Mar 16, 2023

03/13-03/24

Demobilize core climber. Continue below-grade work along west and north of A-2 site. Prepare for assembly of East arch (alongside WTC Ave). Continue...
Mar 9, 2023

03/06-03/17

Tower Core Wall Reinforcement & Installation (Level 17-Roof) Steel arch assembly for South Arch (opposite Congress Street) Steel frame erection of Level 01...
Mar 3, 2023

02/27-03/10

Continue installation of pile caps, waterproofing, and grade beams Concrete Tower Core (Levels 13-16) Steel arches have arrived! Assembly starting along...
Feb 2, 2023

UPCOMING WORK

01/30-02/10 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
Jan 26, 2023

UPCOMING WORK

01/23-02/03 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
Jan 19, 2023

UPCOMING WORK

01/16-01/27 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
Jan 10, 2023

UPCOMING WORK

01/09-01/20 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...