Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...
Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...
Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...
Steel/Deck Erection (roof decking & framing) Slab on Deck reinforcements and MEP penetrations (L17) Concrete Slab on Deck Placements (L17 South and L17...
Steel/Deck Erection (roof decking & framing) Slab on Deck reinforcements and MEP penetrations (L17) Concrete Slab on Deck Placements (L17 South and L17...
Steel/Deck Erection(18 Metal Decking, 18&19 framing) Slab on Deck reinforcements and MEP penetrations (L16 and L17) Concrete Slab on Deck Placements (L15...
Steel/Deck Erection(18 Metal Decking, 18&19 framing) Slab on Deck reinforcements and MEP penetrations (L16 and L17) Concrete Slab on Deck Placements (L15...
Complete Steel Framing & Decking through Roof Topping Out Ceremony to take place Thursday 10/26: 11am-1pm @ WTC Ave Plaza Install Monument Stair between...
Complete Steel Framing & Decking through Level 09 Complete Concrete Placement through Level 07 Excavation for Basement along Congress Street Start Spray...
Complete Steel Framing & Decking through Level 08 Complete Concrete Placement through Levels 04 Excavation for Basement along Congress Street Start Spray...
Complete Steel Framing & Decking through Level 07 Complete Concrete Placement through Levels 02 Form & pour Level 03 deck Excavation for Basement along...
Complete Steel Framing & Decking through Level 06 Complete Concrete Placement through Levels 02 Complete Steel Framing through Level 07 Form & pour Level 03...
Complete Steel Framing & Decking through Level 05 Complete Concrete Placement through Level 02 Continue Steel Framing through Level 06 Form & pour Level 03...
Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...
Grade beams complete – continue utilities connections on site. Continue Level 02 south framing (see below re: Ramp F traffic impacts) Start assembly of West...
Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Levels 2 - 3. Continued below-grade work throughout...
Patriots’ Day / Marathon Monday (04/17): No work on site. Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at...
Continue below-grade work along west and north of A-2 site. Continue steel assembly / detailing at Level 03. Pour tower core slab Levels 04-05 Continue...
Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...
Continue below-grade work along west and north of A-2 site. Continue assembly of East arch (alongside WTC Ave). Continue steel assembly / detailing at Levels...
Demobilize core climber. Continue below-grade work along west and north of A-2 site. Prepare for assembly of East arch (alongside WTC Ave). Continue...
01/30-02/10 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
01/23-02/03 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
01/16-01/27 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
01/09-01/20 Triangle Parcel: Continued utilities work Continued installation of grade beams in preparation for steel structure ○ Parcel A-2: Continue...
During the first week of December, foundation work was completed, including the installation of LBE's, Drilled-in Mini Piles, and Pressure Injected Footings...
In October, the first phase of the custom art scrim project was installed at the Congress Street level. In addition to showcasing 21 custom art pieces from a...