FEATURED STORY

05/07 - 5/24

  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Spray Fireproofing  (Patching)
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • ...

FILTER BY

Jan 18, 2024

1/15 - 1/26

Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...
Jan 11, 2024

1/2 - 1/12

Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck Placements (roof level) Spray...
Jan 4, 2024

1/2 - 1/12

Steel Detailing(roof level) Elevator Support Steel Installation Slab on Deck reinforcements and MEP penetrations (roof level) Concrete Slab on Deck...
Dec 21, 2023

12/18 - 12/29

Steel/Deck Erection (roof decking & framing) Slab on Deck reinforcements and MEP penetrations (L17) Concrete Slab on Deck Placements (L17 South and L17...
Dec 14, 2023

12/11 - 12/22

Steel/Deck Erection (roof decking & framing) Slab on Deck reinforcements and MEP penetrations (L17) Concrete Slab on Deck Placements (L17 South and L17...
Dec 7, 2023

12/05 - 12/15

Steel/Deck Erection(18 Metal Decking, 18&19 framing) Slab on Deck reinforcements and MEP penetrations (L16 and L17) Concrete Slab on Deck Placements (L15...
Nov 30, 2023

11/28 - 12/8

Steel/Deck Erection(18 Metal Decking, 18&19 framing) Slab on Deck reinforcements and MEP penetrations (L16 and L17) Concrete Slab on Deck Placements (L15...
Nov 9, 2023

11/06 - 11/17

Complete Concrete Placement through Level 15 Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 12) Continue prep for...
Nov 2, 2023

10/30 - 11/10

Steel framing complete through roof Install Monument Stair between Levels 01-02 Complete Concrete Placement through Level 14 Continue Intumescent Paint &...