Contact
Feb 27, 2024

2/12 - 2/23


  • Concrete Slab on Deck Placements (roof level)
  • Spray Fireproofing  (Dome Ceiling)
  • Mechanical / Elevator shaft framing
  • Lobby MEPs
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM.
  • Curtain Wall Installation (Levels 09-10)
  • Spray Insulation Application- Dome Ceiling and Loading Dock
  • Concrete placement – Grand Staircase

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Removal of South Protective Deck (Local Traffic Impacts -- March 2024, details pending)
  • Tower Crane Dismantle (Local Traffic Impacts – March 2024, details pending)