4/8 - 4/26
Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical...
Continue Levels 03-04 framing
Continue steel welding & decking at Triangle Parcel (park)
See night/weekend work for Pedestrian Bridge information
Operation & hours are pending final approval from public agencies.
Traffic advisory to be distributed ASAP upon confirmation from agencies.