4/8 - 4/26
Penthouse- Framing, Equipment- Connections/Rough MEP Install Spray Fireproofing (Patching, Triangle) Mechanical Riser Install/Shaft Framing Rough Mechanical...
Continue Levels 03-04 framing
Continue install of overhead protection work at highway ramp
Continue steel assembly / detailing on Triangle Parcel
Demobilize crawler crane from within Parcel A-2.
See Traffic Advisory. Abutters and MBTA to use Seaport Lane. General Public to use D Street.