Feb 23, 2023

UPCOMING WORK

02/21-03/03

Triangle Parcel:

  • Continued utilities work
  • Continued installation of grade beams in preparation for steel structure

Parcel A-2:

  • Continue installation of pile caps, waterproofing, and grade beams
  • Concrete Tower Core (Levels 11-15)
  • Steel arches tracking for end-February delivery (assembly starts 1st week March)

Night Work:

  • No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no noise impacts)

Weekend Work:

            Saturday day-shifts will be requested / approved on case-by-case basis. No traffic or noise disruptions anticipated.

Union Construction Holidays (No Work On Site):

            Next Construction Holiday: Monday April 17th (Patriot’s Day / Marathon Monday)