Oct 26, 2023

10/23-11/03

  • Complete Steel Framing & Decking through Roof
    • Topping Out Ceremony to take place Thursday 10/26: 11am-1pm @ WTC Ave Plaza
  • Install Monument Stair between Levels 01-02
  • Complete Concrete Placement through Level 13
  • Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 11)
  • Continue prep for curtainwall through Level 14
  • Eversource Permanent Power installation @ Congress Street: awaiting confirmation of timing.
    • Work expected to be complete before November 15th
  • Continue MEP riser installations in building core through Level 10

Night & Weekend Work:

  • Overnight cut & cap of water / sprinkler service (Seaport West/Hotel): Monday 10/30 (11pm-5am).
  • Saturday Day Shift Work to be requested on case-by-case basis.

 

Upcoming Holidays:

  • Thanksgiving: Thursday November 23, 2023