- Complete Concrete Placement through Level 15
- Continue Intumescent Paint & Spray Fireproofing of lower levels (through Level 12)
- Continue prep for curtainwall through Level 16
- Eversource Permanent Power installation @ Congress Street
- Continue MEP riser installations in building core through Level 11

### Night & Weekend Work:

- Saturday Day Shift Work to be requested on case-by-case basis.
- Concrete pour @ pedestrian bridge is in planning phase with MassDOT

### Upcoming Holidays:

- Thanksgiving: Thursday November 23, 2023

 

[View full post](https://www.10worldtrade.com/construction-updates/november72023)

```json
{
  "@context" : "http://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Author Name"
  },
  "dateModified" : "2023-11-09T19:00:01.196Z",
  "datePublished" : "2023-11-09T19:00:00Z",
  "headline" : "11/06 - 11/17",
  "image" : {
    "@type" : "ImageObject",
    "height" : 540,
    "url" : "https://9017812.fs1.hubspotusercontent-na1.net/hubfs/9017812/Picture1-Nov-07-2023-06-37-39-5654-PM.png",
    "width" : 405
  },
  "mainEntityOfPage" : "https://www.10worldtrade.com/construction-updates/november72023",
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "height" : 60,
      "url" : "/hs/hsstatic/content_shared_assets/static-1.4092/img/default-amp-logo.png",
      "width" : 60
    },
    "name" : "Construction Updates"
  }
}
```