Jan 19, 2023

UPCOMING WORK

  • 01/16-01/27
    • Triangle Parcel:
      • Continued utilities work
      • Continued installation of grade beams in preparation for steel structure
    ○ Parcel A-2:
      • Continue installation of pile caps, waterproofing, and grade beams
      • Concrete Tower Core (target first 100ft vertical by early February)
      • Steel arches tracking for mid-February delivery
  • Night Work:
      • No night work on the 2-week look ahead (possibility for occasional checks on blanketing / heating of concrete but no construction work)
  • Weekend Work:
      • Saturday day shifts to be requested on case-by-case basis, and limited to daytime hours only with no noise or traffic impacts permitted.
  • Union Construction Holidays (No Work On Site):
      • Monday February 20th (Presidents’ Day)