Construction Updates | 10 World Trade

12/18 - 12/29

Written by Author Name | 12/21/23 7:00 PM

  • Steel/Deck Erection (roof decking & framing)
  • Slab on Deck reinforcements and MEP penetrations (L17)
  • Concrete Slab on Deck Placements (L17 South and L17 North)
  • Spray Fireproofing (L13, L1-L3)
  • Curtain Wall Installation (L2-L4)
  • Triangle Foundation Wall Placements

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Planned Night Work: Second Shift of hoist jump scheduled for 12/11-12/15

Upcoming Holidays:

  • Christmas Day: Monday December 25, 2023