Construction Updates | 10 World Trade

07/31 - 08/11

Written by Author Name | 8/3/23 6:00 PM

  • Complete Steel Framing & Decking through Level 08
  • Complete Concrete Placement through Levels 04
  • Excavation for Basement along Congress Street
  • Start Spray Fireproofing of lower levels
  • Form & pour tree pits for Triangle Parcel landscape
  • Continue hardscape work @ WTC Ave
  • See night/weekend schedule below for look-ahead related to traffic & noise impacts.

Night & Weekend Work:

  • No road / lane closures during Sumner Tunnel Rehabilitation Project (July 1 – September 1)
  • Saturday Day Shift Work to be requested on case-by-case basis. No weekend night work expected
  • Eversource work @ Haul Rd (back of house Omni Hotel): coordination ongoing.