Construction Updates | 10 World Trade

4/22 - 5/10

Written by Author Name | 4/25/24 6:00 PM

  • Penthouse- Framing, Equipment- Connections/Rough MEP Install
  • Spray Fireproofing  (Patching)
  • Mechanical Riser Install/Shaft Framing
  • Rough Mechanical Installation
  • Curtain Wall Bunk deliveries Monday-Wednesday 3-7PM. 
  • Curtain Wall Installation L16/17-Upcoming
  • Lobby MEP Installation
  • Lobby Rough Framing- Core Wall and Dome Ceiling
  • Lobby Storefront Glass Install
  • Elevators- Service Cars and Low Rise Ongoing, High Rise Enabling Work
  • Domestic/Fire Protection Line Install Within Site

 

Night & Weekend Work:


  • Saturday Day Shift Work to be requested on case-by-case basis.
  • Pedestrian Bridge Placement #2